In early 2008, the groups convened at a strategic planning workshop, and identified a common goal for 2015 – to build from existing strengths and ensure that the cluster is recognised as one of the world's leading precincts for regenerative medicine. A working group was formed to progress the initiative and is currently developing a strategic plan for the 2009 – 2015 period. The draft strategic plan for the South East Melbourne Alliance for Regenerative Therapies (SMART) is due to be completed in November 2008, for review by the wider group of stakeholders in December 2008.

In the near term, the working group has initiated a number of activities to enhance collaborative links between the different organisations. For example, a series of multidisciplinary workshops have been held throughout mid 2008, leading to a number of new collaborative research projects to be joint-funded by ARMI, CSIRO, ASCC and Monash University Departments. Additional workshops and regular seminars are planned to identify and support opportunities for further joint projects.

Date   Planned activity
Feb 2008   Inaugural workshop (included involvement from wide range of local research groups)
March 2008   Working group commences: Silvio Tiziani (ARMI), Keith McLean (CSIRO), Stephen Livesey (ASCC), Bryan Williams (MIMR), Margaret Hansford. Identifies near-term actions and need for longer term strategic plan.
June 2008   Project Officer, Heather St John, appointed for development of strategic plan
July 2008   Multidisciplinary workshop involving  engineers, biologists and chemists. Three new joint projects identified & need for local seminar series
August 2008   Information gathering phase. Input from local organisations with capabilities in regenerative medicine.
September 2008   Working group to develop proposed initiatives in line with longer term strategic objectives of participating organisations
October 2008   Draft strategic plan to be circulated to working group for review
November 2008   Amendment of draft strategic plan and endorsement by working group
December 2008   Distribution of draft strategic plan to broader workshop group. Forum.
Jan – June 2009   Refinement of Major Program Initiatives
July – Dec 2009   Program ramp up
2010 – 2015   Implementation of Major Program Initiatives

 

 

Image courtesy of MISCL